Amend contract for New City Impound Building Project
Latest action, July 3, 2018: Adopted 9-0-0-0
1 meeting on record, oldest first.
-
Step 1
July 3, 2018A Resolution authorizing the Mayor to amend Contract No. C-17-0161 with Thomas Caldwell, Architect for the New City Impound Building Project, increasing the contract amount by $17,800.00 for a new contract total of $42,400.00, and extending the date of completion to December 31, 2019. (Requested by Fleet Services and Engineering Department)
Resolution authorizing contract amendment
Moved by Finbarr Saunders · seconded by Seema Singh
Share this vote →Aye · 9: Stephanie Welch, Andrew Roberto, Seema Singh, Lauren Rider, Mark Campen, Gwen McKenzie, George C. Wallace, Marshall Stair, Finbarr Saunders
Source: official minutes (PDF) for July 3, 2018, page 6.