Authorize change order for Third Creek Greenway Bridge Replacement Project.

Latest action, July 9, 2013: Adopted 9-0-0-0

1 meeting on record, oldest first.

  1. A Resolution authorizing the Mayor to execute Change Order No. 2 to Contract No. C-13-0032 with Design & Construction Services, Inc., for the Third Creek Greenway Bridge Replacement Project, increasing the contract price by $36,199.10 for a new contract total of $232,722.10, and extending the completion date to July 31, 2013.(Requested by Department of Engineering)

    Source: official minutes (PDF) for July 9, 2013, page 5.