Authorize change order for Third Creek Greenway Bridge Replacement Project.
Latest action, July 9, 2013: Adopted 9-0-0-0
1 meeting on record, oldest first.
-
Step 1
July 9, 2013A Resolution authorizing the Mayor to execute Change Order No. 2 to Contract No. C-13-0032 with Design & Construction Services, Inc., for the Third Creek Greenway Bridge Replacement Project, increasing the contract price by $36,199.10 for a new contract total of $232,722.10, and extending the completion date to July 31, 2013.(Requested by Department of Engineering)
Moved by Nick Pavlis · seconded by Finbarr Saunders
Share this vote →Aye · 9: Nick Pavlis, Duane Grieve, Brenda Palmer, Nick Della Volpe, Mark Campen, Daniel T. Brown, George C. Wallace, Marshall Stair, Finbarr Saunders